NOVARYNINDUSTRIAL LIMITED

Quality / compliance / traceability

The release is part of the product.

A thermal unit is only as good as the record that travels with it. Novaryn controls design inputs, material traceability, fabrication, testing and release through one quality file.

Quality system
ISO 9001:2015
Pressure equipment
ASME U / U2 / S · PED H
Traceability
EN 10204 3.1
Release
Project ITP
Cooling equipment on a power transformer
Novaryn equipment referenceTX / US

Certifications

The approvals behind the nameplate.

Certification scope follows the equipment family, pressure class and project specification. The table shows the current system approvals; the order certificate names the exact scope.

ApprovalScopeBodyStatusRecord
ISO 9001:2015Quality management systemLRQACurrentRequest
ISO 14001:2015Environmental managementLRQACurrentRequest
PED 2014/68/EUPressure equipment — Module HTÜVCurrentRequest
ASME U / U2Pressure vessels — Div. 1 and Div. 2ASMECurrentRequest
ASME SPower boilersASMECurrentRequest
IEC 60076-7Transformer cooling qualificationInternalTestedRequest

Quality gates

Five gates. No silent handovers.

Each gate has a defined output and a named owner. The project quality plan can add witness points, hold points and third-party inspection without changing the sequence.

Quality policy

Build the equipment and the record together. No release without traceability; no shipment without the controlling revision.

01

Design input review

Duty point, media, design conditions, standards, interfaces and document requirements are checked before engineering release.

Output

Reviewed basis of design

02

Material control

Heat-number traceability, mill certificates, incoming inspection and material segregation against the bill of materials.

Output

EN 10204 3.1 file

03

Fabrication control

Welder qualification, WPS/PQR, dimensional checks, NDT and hold points recorded against the inspection plan.

Output

Signed ITP

04

Test & release

Pressure test, leak test, performance check where applicable and final inspection before the release certificate.

Output

Test records + certificate

05

Project handover

As-built drawings, manuals, spare list, material reports and digital record indexed to the serial number.

Output

Handover dossier

Inspection & test

What we verify, and how.

The test regime is selected from the pressure class, media, standard and project specification. Additional witness, NDT or performance testing is quoted against the inspection plan.

01

Hydrostatic / pneumatic test

Pressure test at the specified test pressure, with hold time, water quality and drying route recorded against the unit.

Pressure test certificate

02

Helium / trace leak test

Helium or tracer-gas leak testing for refrigerant, hydrogen, cryogenic and high-integrity circuits.

Leak test record

03

Non-destructive examination

Dye penetrant, magnetic particle, ultrasonic or radiographic examination selected by joint type and specification.

NDT report

04

Dimensional inspection

Envelope, nozzle orientation, connection sizes, lifting points and interface dimensions checked against the GA drawing.

Dimensional report

05

Performance verification

Where the contract requires it, thermal performance is verified from the test data or a witnessed factory run.

Performance test report

06

Final inspection & release

Painting, tagging, preservation, packing and document completeness checked before the release certificate is signed.

Release certificate

Traceability

Every pressure boundary has a heat number.

Material certificates are matched to the bill of materials, the purchase order and the serial number. The file can be searched by heat number, component or drawing revision.

  • Mill certificates to EN 10204 3.1
  • Heat-number mapping to pressure-retaining parts
  • NACE MR0175 review for sour service
  • PMI verification on selected alloys
  • Serial-number indexed handover dossier
Shell and tube exchanger under inspection

Inspection / material verification

Records are reviewed before the unit enters the release queue.

Quality / project

Add the quality plan to the enquiry.

Tell us the applicable standard, inspection class, witness requirements, material certification and any third-party review. The quotation will carry the inspection plan and document schedule.